2012
May 16 - Signed contract with Ryan Homes
May 30 - Finalized structural changes
June 2 - Flooring selections made
June 3 - Color choices with SR
June 7 - Guardian selections made
June 26 - NVR loan approved
Lots of Waiting...
September 10 - Pre-appraisal completed
A Little More Waiting...
October 25 - Pre-construction meeting
November 9 - Groundbreaking
November 12 - Footers poured
November 13 - Basement/foundation wall forms installed and concrete poured
November 16 - Waterproofing installed
November 13 - Basement/foundation wall forms installed and concrete poured
November 16 - Waterproofing installed
November 21 - Lumber delivered and framing started
December 3 - Framing of first and second floor completed, roof started
December 5 - Plumbing started
December 3 - Framing of first and second floor completed, roof started
December 5 - Plumbing started
December 10 - Basement and Garage concrete floors poured
December 12 - Guardian walkthrough
December 14 - Electrical walkthrough (and rough placement of all those can lights!)
December 20 - Pre-Drywall Meeting
December 27 - Siding and drywall delivered
2013
January 3 - Siding and drywall installed
January 9 - Drywall finishing started
January 11 - Stone installation scheduled